Where the campuses go, and the condition each site must meet.
Liquidata deploys wherever power can be delivered on its customers' timetable: in leased space, on powered sites and with energy and site partners. Its pipeline spans the European Union and the United States and several kinds of power. Site details, capacities and sponsors are shared under confidentiality; capacities are as stated by sponsors and remain subject to diligence [1].
Three kinds of site, described by type.
The sites differ in where their power comes from and in how far their connection has progressed. What they have in common is a sponsor that holds land and a grid position, and a path to at least 100 MW of IT load that can be stated in signed documents or shown to be within reach of them.
Technology-park sites with a grid supply assurance and a phased connection, and a regional expansion platform behind them.
400/220/110 kV
Brownfield industrial platforms with current grid approvals and room to expand, adjoining transmission substations, with on-site gas-to-power options and storage integration.
Gas-to-power options
A campus with on-site combined-cycle generation and substation, and powered land with as-of-right data-center zoning, power available now and a utility study for expansion.
Utility studies
How sites are sequenced, and why connection rights now expire.
Sites are sequenced by the date on which power can be delivered and by where customers want their capacity. Connection rights are no longer held indefinitely. Across the European Union and the United States, operators and regulators have moved in the last two years to rules under which a connection position lapses if it is not used within a fixed period, often 12 to 18 months, requires financial security per megawatt until energization, or is terminated for missed procurement, financing and offtake milestones; several now give priority to sites that bring their own storage or generation [2]. A sponsor that holds a connection therefore has a reason to see it used on time, and a tenant that cannot show a customer on time is a risk to the sponsor's position.
Liquidata's sequencing rule follows from this. No site is committed until power, permits and delivery dates are confirmed in signed agreements, and no hardware is ordered until the capacity is under contract and the site's energization dates are in a signed connection agreement. The pipeline's grid capacity, as stated by its sponsors, is a multiple of what the planned campuses need, so each campus goes where at least 100 MW of IT load can be energized within 24 months and where power, price and demand line up, and a site owner is never asked to hold capacity for a campus that has not been sold.
What the figures on this page rest on.
Manufacturer specifications are as published; regulatory figures are as adopted or proposed on the dates given; estimates are identified as estimates. Where a figure is Liquidata's own design assumption, the text says so.
- Capacities and connection positions are as stated by sponsors and remain subject to diligence; none is a commitment by Liquidata or by the sponsor until the definitive agreements are signed.
- Connection regimes adopted or proposed in 2025 and 2026 by transmission operators and regulators in the European Union and the United States, including validity limits on connection conditions, financial security per megawatt and milestone-based termination; the examples with figures are given on the Energy to Compute page, sources 2 to 7.