Energy to Compute

A second route for powered sites, and the reasoning behind it.

For developers, energy companies and infrastructure investors that hold deliverable power. This page explains why Liquidata deploys on such sites rather than building its own, how a site owner takes part, what a campus requires from a site, and the efficiency figures a site owner, a grid operator and a permitting authority will ask for. The terms of each site partnership are agreed site by site under confidentiality and are not published.

The reasoning

Why deliverable power, not hardware, sets the timetable.

The International Energy Agency estimates that data centers consumed about 415 TWh of electricity in 2024 and projects about 945 TWh in 2030 in its base case, with artificial intelligence the largest contributor to the increase [1]. The constraint on meeting that demand is the grid connection, and transmission operators and regulators across the European Union and the United States have begun to ration it. The Irish operator accepts no new data-center connections in the Dublin area before 2028 [2]. The Polish operator's published capacity map shows no available transmission capacity for new connections at any substation for 2026 or 2031 [3]. The Greek operator reported data-center connection requests above 4.5 GW against about 520 MW of final connection offers issued by mid-2026 [4]. Great Britain's regulator has proposed credit support of £237,500 to £712,500 per MW until energization, with termination for missed procurement and offtake milestones [5]. Texas adopted large-load interconnection rules in 2026 that require financial security per megawatt and report projects whose schedules slip [6]. In Northern Virginia, the largest data-center market in the world, the utility has told large new loads to expect waits of several years for a connection [7]. Lead times for large power transformers and high-voltage switchgear have lengthened to several years [8].

The consequence is that a site with a signed connection agreement and dated energization is the scarce input, and the party that holds it holds the input that limits the rate at which capacity can be built. When such a site is sold or leased, the price is set before any compute revenue exists; utilization, service margin, renewals and the enterprise value of recurring revenue accrue to the buyer and its tenants. An operating partner that brings the customers and builds and runs the compute on the owner's site gives the site owner and its investors a second route, in which their involvement does not end on the day of the transaction and they do not have to become a cloud operator.

Service
Customers, product, operations and service levels
Liquidata, provider of record

Four layers, each owned and financed on its own terms. Power and site stay with the developer and its investors. Compute equipment is financed against customer contracts. Liquidata owns the service: it signs and invoices the customers, runs the service and is accountable for it.

The commercial model follows from the layers: the site owner or its project company supplies site capacity, power and energy services, and Liquidata contracts with the customers. The terms on which a site owner takes part are agreed site by site and provided under confidentiality.

A module on a site

What a module and a campus require from a site.

The numbers a site owner needs first: load, energy and firming. Every figure follows from NVIDIA's published rack power of about 190 kW and a design PUE of 1.25; the campus figures are ten times the module.

IT load
10 MW
per module: 50 racks at about 190 kW, plus 5% for network and storage; 100 MW per campus of ten
Facility load
12.5 MW
per module at a design PUE of 1.25, liquid-cooled; about 125 MW per campus
Electricity
109 GWh
a year per module, a flat 24/7 load; about 1.1 TWh a year per campus
Firming
80 h
that a 1,000 MWh storage station carries one module; about 8 hours for a campus

A campus is the unit Liquidata deploys, because the largest buyers of capacity plan in blocks of about 100 MW and on a horizon of about 24 months, and do not consider sites below that size or beyond that horizon, whatever their other merits. A site therefore qualifies for a campus when at least 100 MW of IT load, about 125 MW at the meter, can be energized within 24 months under a signed connection agreement with dates. Within a campus, modules are contracted against signed demand and confirmed power and timed to the site's energization.

Sites with their own generation and storage can offer firm, low-carbon power to a compute tenant and schedule suitable workloads around output and prices. The delivered power price is agreed in the site terms and is, after the connection date, the second variable in deciding where a campus goes.

Efficiency

Energy, water and heat, as specifications.

A module's efficiency is a specification, set at design and reported in operation, not a program. The figures below are the ones a site owner, a grid operator and a permitting authority ask for first, and the ones the strictest rules in the European Union now require: Germany's Energy Efficiency Act sets a PUE of 1.2 for data centers commissioned from July 2026 and requires heat reuse rising from 10% to 20% over 2026 to 2028, and the EU Energy Efficiency Directive requires data centers above 500 kW to report their energy performance [9]. Each figure follows from the choice of a warm-water, liquid-cooled platform, as explained on the home page.

Design PUE
1.25
assumed in the module economics; the warm-water design is specified to 1.2 where a site's rules require it. The industry average reported by the Uptime Institute has stayed between 1.5 and 1.6 for several years [10]
Water
Near zero
consumed for cooling: 45 °C loops reject heat to dry coolers, with no evaporative towers; adiabatic assist, where used, consumes water only in the hottest hours
Heat
20 MW
of heat at 45 °C or more from a 100-rack module, offered to district or industrial heat networks where a taker is within reach, raised by heat pumps to network temperatures
Supply
24/7
flat load, matched to renewable output and storage where the site owner provides them; sites with storage ride through grid events

Each site reports PUE, water use and heat reuse as the EU Energy Efficiency Directive requires of data centers above 500 kW.

What each side brings

What each side brings.

The site

Land, a signed grid connection agreement for at least 100 MW of IT load with energization dates inside 24 months, and the permits. Power, storage and energy services. Buildings and cooling, with infrastructure investors where wanted.

Liquidata

The customers and their contracts. Cluster design, delivery and operations. The compute equipment and its financing. The service, and accountability for it.

Sources and notes

What the figures on this page rest on.

Manufacturer specifications are as published; regulatory figures are as adopted or proposed on the dates given; estimates are identified as estimates. Where a figure is Liquidata's own design assumption, the text says so.

  1. International Energy Agency, Energy and AI (April 2025).
  2. EirGrid, statements on data-center connections in the Dublin region (2022 onward): no new connections in the area before 2028.
  3. Published connection-capacity maps of the Polish transmission operator (PSE) for 2026 and 2031, as compiled in industry reports of 2026.
  4. Figures of the Greek transmission operator (IPTO) on data-center connection requests and final connection offers, as reported in mid-2026.
  5. Ofgem, consultation on data-centre connection reforms (2026), as summarized by counsel: proposed credit support per MW and milestone-based termination.
  6. Public Utility Commission of Texas, large-load interconnection rules adopted in 2026.
  7. Dominion Energy, statements to customers and regulators on connection timelines for large new loads in Northern Virginia (2024 to 2025).
  8. Industry surveys of lead times for large power transformers and high-voltage switchgear (2024 to 2026).
  9. Germany, Energy Efficiency Act (Energieeffizienzgesetz, 2023): PUE of 1.2 for data centers commissioned from July 1, 2026 and heat-reuse requirements of 10%, 15% and 20% for 2026, 2027 and 2028; EU Directive 2023/1791 on energy efficiency, reporting for data centers above 500 kW.
  10. Uptime Institute, Global Data Center Survey (2024 and 2025 editions): industry average PUE.